COMPLETED |
 |
Completed Projects
Item
|
WORK DESCRIPTION
|
Type of Contract
|
CLIENT
|
LOCATION
|
EXECUTION DATE
|
1
|
Construction of two 32 “ Inter-phases Gas Pipelines from Phases 9 & 10 to Phases 15 & 16, 7 km Length - South Pars Gas field Development
(Contract No. 2012/3245/002)
|
C
|
NIOC /
POGC - SGK
(Sanat Gostar Kish)
|
Asaluyeh - Boushehr
|
2013
|
2
|
Construction of 32” Inter-phases Gas Pipeline from Phases 6, 7, & 8 to Phases 15 & 16, 2 km Length - South Pars Gas field Development
(Contract No. 2012/3076)
|
C
|
NIOC /
POGC - IOEC
|
Asaluyeh - Boushehr
|
2012
|
3
|
Engineering, Procurement, and Construction of 32” Gas Pipeline, Valves, and Connections, Phase 1 - South Pars Gas field Development
(Contract No. 639-89-35)
|
EPC
|
NIOC /
POGC
|
Asaluyeh - Boushehr
|
2009
|
4
|
Engineering, Procurement, and Construction of 32” Inter phases Gas Pipeline from Phases 6, 7, & 8 to Phases 9 & 10 and Manifold Installation at Phases 6, 7, & 8, 7.5 km Length - South Pars Gas field Development
(Contract No. 506-87-35)
|
EPC
|
NIOC /
POGC
|
Asaluyeh - Boushehr
|
2008
|
5
|
Construction of 32” Inter-Phase Pipeline Connecting Phase 1 to Phases 9 & 10, 6.4 km Length - South Pars Gas field Development
(Contract No. 1112/2254)
|
C
|
NIOC /
POGC - IOEC
|
Asaluyeh - Boushehr
|
2007 - 2008
|
6
|
30”Gas Transfer Pipeline for Gas Gathering Station No. 2, 35 km Length - Tabnak Gas Field Development
(Contract No. NTM-82-229)
|
PC
|
NIOC / PEDEC
|
Tabnak Gas Field - Boushehr
|
2003 - 2005
|
7
|
Engineering, Procurement, and Construction of Tabnak Gas Field Surface Facilities - Tabnak Gas Field Development
(Contract No. MED-80161-ME01)
|
EPC
|
NIOC / PEDEC
|
Tabnak Gas Field - Boushehr
|
2002 - 2005
|
8
|
Construction of Asaluyeh Phase III Refined 56” Gas Transfer Pipeline, 36 km Length - South Pars Gas field Development
(Contract No. 020-78-728-PKN)
|
C
|
NIOC /
POGC
|
Kangan- Asaluyeh - Boushehr
|
1999 - 2001
|
9
|
Construction of Karanj – Parsi Gas Injection Facilities – Karanj/Parsi Oil Field Development
(Contract No. 34-73-01524)
|
C
|
NIOC
|
Karanj – Parsi Oil Field - Khuzestan
|
1996
|
10
|
Construction of 16” Gas Transfer Pipeline, 96 km Length – Ray/Garmsar
(Contract No. 302/8858)
|
C
|
NIGC
|
Ray – Garmsar
|
1989 - 1993
|
11
|
Construction of 10” Condensate Handling Pipeline, 42 km Length - Kangan Gas Refinery
(Contract No. 98/KTGT)
|
C
|
NIOC
|
Kangan - Tahery
|
1987 - 1990
|
12
|
Construction of 16” Crude Oil Pipeline (2nd section), 250 km Length – Tehran/Tabriz
(Contract No. 952CC)
|
C
|
NIOC
|
Tehran-Tabriz
|
1985 - 1987
|
|
|