32” Gas Pipeline, Valves, and Connections Phase 1

 

Engineering, Procurement, and Construction of 32” Gas Pipeline, Valves, and Connections Phase 1 - South Pars Gas field Development

 

 Client:

 Pars Oil & Gas Company (POGC)

 Contract starting date:

 September 2009

 Contract completion:

 Completed

 Contract No.:

 639-89-35

 Location:

 Asaluyeh - (Boushehr Province)

 Pipelines diameters and lengths:

 32 in, Inside Plant

The project comprises engineering, procurement, construction, installation, and commissioning for replacement of existing interconnecting 20” gas pipeline at phase 1 of south pars gas field with a 32” pipeline.

Pipeline diameter is 32” and approximate length is 150m and includes one insulating joint, one flow meter, one ESD valve, one check valve, and other materials and contains following sections:

  •  Engineering
    • Surveying
    • Detail engineering
    • Field engineering
    • Construction, installation, and commissioning drawings, procedures, and calculations
    • Final documentation
    • Precommissioning and commissioning engineering
    • Managing coordinating with other companies and groups
    • Material tracing system
  • Procurement
    • Preparation of purchase documents
    • Preparation and submission of purchase orders after Client approval
    • Material expediting
    • Material insurances
    • Material inspection by TPA and obtaining certifications from Client and TPA
    • Packing
    • Loading, transportation, unloading, and customs clearances (if applicable)
    • Planning and control of all purchase activities
    • Material storage
  • Construction
    • Construction of 32” pipeline
    • Construction and installation of piping, valves, fittings, and instrumentation
  • Commissioning
  •  Mobilization and Demobilization